The works being undertaken today consist of tarmacing the area of carriageway where we removed the existing 'table top'. We shall also be adjusting ironwork and excavating kerbs.
Our works planned for tomorrow will involve removing the existing build-outs, excavating kerbs and re-installing them on the new kerb line.
Our Public Liaison Officer for this scheme is Terry Godwin. He will be on site on a regular basis and will be able to answer any questions that you may have. Alternatively we can be contacted on our Customer Care Line 01905 761176 or by email roadworks.info@ringway.co.uk
We will be updating this blog on a daily basis (Monday to Friday) now that the works have commenced with information on the progression of this scheme. Information on our other roadworks throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info
We appreciate your patience and understanding whilst we carryout these improvement works.